We
all know that parking at the Jetport is often very limited,
that's why we’re building a new parking garage. We
also realize that things will change in the future. So,
based on our projections and our 1% average annual growth
over the past ten years, the new facility should carry us
through 2011.
Building
for tomorrow, planning for beyond
But, we didn’t let the process end here. We looked
out 15 years or more – at what potential increases
in demand there might be – and outlined plans for
Phase II and Phase III. While we have set no timetable for
these additional steps, it made sense to us to be prepared.
Please
take a moment to view the drawings below. They show our
Current Parking situation, Phase
I improvements (the garage now under construction),
and a look at Phase II and Phase
III. With each phase of these improvements, we’ve
highlighted a couple of key items.
Current
Parking
Where we are today:
-
Limited spaces
- Often
full
Phase
I
- New
six-level parking structure
- Adds
1,480 spaces – doubling the available public parking
- Construct
new perimeter road improving traffic flow
- View
photos and artist
drawing
Phase
II
- Demolish
current parking structure
- Construct
new six-level facility
- Adds
1,283 spaces
Phase
III
-
Construct new six-level garage
- Adds
2, 045 spaces